Популярное

Музыка Кино и Анимация Автомобили Животные Спорт Путешествия Игры Юмор

Интересные видео

2025 Сериалы Трейлеры Новости Как сделать Видеоуроки Diy своими руками

Топ запросов

смотреть а4 schoolboy runaway турецкий сериал смотреть мультфильмы эдисон
dTub
Скачать

Complete tutorial What is resource loading in P6 | how to calculate resources | Productivity Rates |

Автор: PLANNING - P6

Загружено: 2023-01-01

Просмотров: 37255

Описание:

🔴 WHAT YOU'LL LEARN/SEARCH TITLES:

✅Understanding direct, indirect, labor, non-labor & material resources
✅How to calculate productivity (with and without productivity norms)
✅How to identify the “main resource” for each activity
✅How to prepare a complete resource loading sheet in Excel
✅How to calculate manpower, equipment hours & material quantities
✅ How to convert units (sft, rft, sqm, m³, kg, etc.)
✅Crew production & role-based resource assignments
✅Step-by-step cost calculation for each resource
✅How to prepare resource leveling strategy if resources are limited
✅How to upload all resources into Primavera P6 accurately
✅How to assign resources, update units, and apply cost resources
✅How to read and analyze resource usage profiles in P6
✅How to prepare staffing plans, consumption reports & resource histograms
✅Preparing activity-level productivity using international norms
✅Creating your own productivity norms if your organization doesn’t have them
✅Calculating man-hours, crew-hours & equipment hours
✅Example resources: surveyor, helper, operator, roller, mason, steel fixer, carpenters, mixers, excavator
✅Material calculations: cement, sand, crushed stone, bricks, water, plywood, shuttering materials
✅Full workflow: Excel → Productivity → Duration → Resource Sheet → Cost Sheet → P6 Import
✅Assigning resources to activities properly (including cost resources)
✅Creating WBS-level, activity-level & resource-level views in P6
✅Generating resource histograms, usage spreadsheets & staffing plans


🔴PRODUCTIVITY RATES/NORMS: https://planningp6.com/downloads/java...

🔴RESOURCE CALCULATION FORMAT/SHEET: https://planningp6.com/downloads/ebook/

🔴PRODUCTIVITY RATES/NORMS DESIGN: https://planningp6.com/downloads/engi...

🔴PRODUCTIVITY RATES/NORMS ROADS: https://planningp6.com/downloads/prod...

🔴DESCRIPTION:

Learn the complete workflow of resource loading, productivity setup, and cost planning in Primavera P6 using a clean, practical method. This tutorial shows you how to calculate labor, equipment, and material requirements, prepare a resource sheet in Excel, build accurate productivity-based durations, apply crew production, assign costs, and upload everything smoothly into Primavera P6. You’ll also see how to review resource usage, staffing, consumption, and histograms the way professional planners do. A simple, clear guide to mastering resource-driven scheduling in Primavera P6.

Resource loading = hours of work per time period / hours of capacity per time period

00:00 – Introduction to Resource Loading in Primavera P6
00:21 – Understanding Project Resources and Productivity Rates
01:12 – Calculating Productivity from Norms or Company Data
01:55 – Identifying Main and Dependent Resources for Activities
02:35 – Resource Leveling with Limited Manpower
03:10 – Direct vs Indirect Resources Explained
04:00 – Project Setup and Activity Breakdown in Primavera P6
05:00 – Preparing the Resource Loading Sheet in Excel
06:20 – Exporting Activities from Primavera P6 to Excel
07:00 – Creating Labor, Non-Labor, and Material Resource Categories
08:20 – Setting Productivity Norms and Activity Quantities
10:00 – Indirect Staffing Plan for Project Teams
11:10 – Assigning Productivity Units: Man-Days vs Man-Hours
12:00 – Calculating Duration Based on Productivity and Resources
15:00 – Establishing Standard Working Hours and Company Policies
18:00 – Example: Surveyor Productivity and Resource Calculation
24:00 – Excavation Productivity and Duration Calculation
28:00 – Manual vs Mechanical Excavation Planning
31:00 – Compaction, Leveling, and Dressing Works
34:00 – Uploading and Assigning Resources in Primavera P6

🔴DISCLAIMER:

This channel does not promote or encourage any illegal activities and all content provided by this channel is meant for EDUCATIONAL purposes only.

✅Copyright Disclaimer:

Under section 107 of the Copyright Act 1976, allowance is made for FAIR USE for purposes such as criticism, comment, news reporting, teaching, scholarship, and research. Fair use is a use permitted by copyright statutes that might otherwise be infringing. Non-profit, educational, or personal use tips the balance in favor of FAIR USE.

#PrimaveraP6 #PlanningP6 #resourcecalculation #resourseloading #ProductivityRates #ProjectManagement #ProjectControls #ProjectPlanning #ResourceAllocation #ResourceManagement #CalculateResources #DetermineProductivity #ResourceOptimization #ResourcePlanning #ResourceLeveling #ResourceCapacity #ResourceUtilization #ProductivityMetrics #EfficiencyMetrics #ProjectPerformance #ProjectCost #ProjectDuration #ProjectTimeline #ProjectRisk #ProjectChange #ConstructionPlanning #EPCProjects #Scheduling #ManpowerPlanning #ProjectScheduler #PlanningEngineer #ExcelToP6 #ResourceSheet #P6Training #PlanningAndScheduling #PlanningP6Tutorials

Complete tutorial What is resource loading in P6 | how to calculate resources | Productivity Rates |

Поделиться в:

Доступные форматы для скачивания:

Скачать видео mp4

  • Информация по загрузке:

Скачать аудио mp3

Похожие видео

How to prepare Resource Deployment and Allocation Plan of project | Resource Register | primaverap6

How to prepare Resource Deployment and Allocation Plan of project | Resource Register | primaverap6

Manpower Resource Loading including S-curve in Primavera P6

Manpower Resource Loading including S-curve in Primavera P6

15 | Как выполнить загрузку ресурсов в Primavera P6

15 | Как выполнить загрузку ресурсов в Primavera P6

Scheduling

Scheduling

What is Negative Float in Primavera P6?

What is Negative Float in Primavera P6?

Primavera Tutorials & Tricks

Primavera Tutorials & Tricks

Primavera P6 Tutorials

Primavera P6 Tutorials

How to fix out of sequence activities in P6 is finally revealed using an excel filter

How to fix out of sequence activities in P6 is finally revealed using an excel filter

20 Project Status/Progress Updating & Schedule & Cost Tracking in Primavera P6

20 Project Status/Progress Updating & Schedule & Cost Tracking in Primavera P6

How To Add Assign Calculate Est Weight Apply Top Down Estimation Primavera P6 | Estimated Weights P6

How To Add Assign Calculate Est Weight Apply Top Down Estimation Primavera P6 | Estimated Weights P6

QUIET TIME WITH JESUS - Soaking worship instrumental | Prayer and Devotional

QUIET TIME WITH JESUS - Soaking worship instrumental | Prayer and Devotional

Resource Loading in Primavera P6 - 5 Tips to make it EASIER

Resource Loading in Primavera P6 - 5 Tips to make it EASIER

Как импортировать действия из Excel в Primavera P6 | Инженер-планировщик | Графики проектов |

Как импортировать действия из Excel в Primavera P6 | Инженер-планировщик | Графики проектов |

How to create Complete Project of Oil & Gas Condensate Storage Tanks Facility Primavera P6 Schedule

How to create Complete Project of Oil & Gas Condensate Storage Tanks Facility Primavera P6 Schedule

Resource Levelling in Primavera P6

Resource Levelling in Primavera P6

How To Use Resources in Primavera P6

How To Use Resources in Primavera P6

Step-by-step tutorial: How to add BOQ as material resources in Primavera P6 using Plannex Excel tool

Step-by-step tutorial: How to add BOQ as material resources in Primavera P6 using Plannex Excel tool

Распределение ресурсов из Excel в Primavera P6 | Советы по распределению ресурсов из Excel в Prim...

Распределение ресурсов из Excel в Primavera P6 | Советы по распределению ресурсов из Excel в Prim...

How to Allocate Resources in Primavera P6?

How to Allocate Resources in Primavera P6?

Free Primavera p6 Training for Oil and Gas Project in 2 Hours | #primaverap6 #engineers

Free Primavera p6 Training for Oil and Gas Project in 2 Hours | #primaverap6 #engineers

© 2025 dtub. Все права защищены.



  • Контакты
  • О нас
  • Политика конфиденциальности



Контакты для правообладателей: [email protected]