Hello viewers,
Uploading another video of RUB update being constructed in Una Himachal. The work is going on very slowly & it was supposed to be over by July 31st , but still there is lots of work pending. Owing to heavy rains, there has been little progress. it might take another 3-4 months before it gets completed.
64651- Amb - Haridwar MEMU arriving at PF-1 of Una( late running by almost 1:30 hrs)
View after heavy rain on 2nd August Morning at 10:00 am, heavy water flow seen where it used to be almost dry..
Thanks for watching!