MOL Campus base slab concreting
Автор: MOL Group
Загружено: 17 дек. 2019 г.
Просмотров: 735 просмотров
4,000 cubic metres of concrete and 48 hours of non-stop work. This is how the second weekend of December 2019 looked like at the construction site of our new HQ, MOL Campus. 70 truck mixers continuously moved between four Budapest concrete factories and the site, to make sure we are ready with the 220cm high, reinforced concrete base slab underneath the 28-story tower building.
Learn more about MOL Campus and follow the construction here: http://molcampus.hu/en/construction