Construction Progress September 2025
Автор: Alex Miquel
Загружено: 2025-09-17
Просмотров: 2344
The project continues to progress, commencing with commissioning activities in some areas.
The work of installing the pipeline through the first 3 km in the coastal mountain is now almost 90% complete. Overall, the pipeline of the conveyance system, including lowering into the trench and soil restoration has reached 815% progress.
The desalination plant has now been energized and we achieved the first motor rotation milestone in the project.
Many challenges remain until the full completion of the project, but the extraordinary team of people at Aguas Horizonte and of our Owner's Engineer are poised to drive this project to a successful completion. ,