Bengaluru Metro || Blue Line || Phase 2B || Airport to Hebbal || SEP 2025
Автор: Sunil H P
Загружено: 2025-09-05
Просмотров: 8327
Blue line updates from Airport to Hebbal. Recorded Date : 05-SEP-2025
Phase 2B - Airport to Hebbal
***********************************************
SEP 2025 Updates
Civil Contractor : PKG2 - NCC LTD - 11.678 KM
PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.
Piling Works Happening and Pier casting Picking up pace.
Package 2 :
Kodigehalli Station :- CC Beam Casting in Progress.
Jakkur Cross Station :- U Girder and I girder erection in progress.
Jakkur Plantation Station : Possible Future Station
Yelahanka / Kogilu Cross Station :- PF and CC Slab casting in Progress
Bagalur Cross Station : PF and CC Slab casting in Progress
Package 3 :
Bettahalasuru Station : Unsure
Chikkajala Station : Possible Future Station
Doddajala Station : PF and CC Slab casting in Progress
Stations done by KIAL :
Airport City Metro Station : At grade station building taking shape
Airport Terminal Metro Station : Civil works complete. Finishing works in progress