How To Create and Format S-Curve in P6 | Activity Usage Profile For Selected & Entire project P6
Автор: PLANNING - P6
Загружено: 2021-06-29
Просмотров: 6991
💡📖✍️WHAT YOU'LL LEARN/SEARCH TITLES:
🔎 How to Customize Activity Usage Profile in Primavera P6
🔎 Primavera P6 Activity Usage Profile Complete Tutorial
🔎 Set Up Resource and Cost Profiles in Primavera P6
🔎 Primavera P6 Graph and Timescale Customization Guide
🔎 How to Display Labor, Non-Labor & Material in Activity Usage Profile
🔎 Primavera P6 Tips: Change Background, Bar Colors & Units Display
🔎 Configure Activity Usage Profile View in Primavera P6
🔎 Primavera P6 Timescale & Calendar Settings Explained
🔎 Resource Usage Profile in Primavera P6 Step-by-Step
🔎 Primavera P6 Visual Customization: Profile Colors & Layouts
🔎 How to Change Profile Scale from Days to Weeks in Primavera P6
🔎 Primavera P6 Activity Usage Chart Customization (Colors + Units)
🔎 Primavera P6 Resource Graph: Practical Guide for Planners
🔎 How to Adjust and Save Profile Views in Primavera P6
🔎 Primavera P6 Display Settings for Activity & Resource Profiles
📢📃📑DESCRIPTION:
In this tutorial, you’ll learn how to use and customize the Activity Usage Profile in Primavera P6.
We’ll cover everything from adjusting time-scale and color settings to showing resource, labor, and cost data, all explained in a practical, easy-to-follow way.
🌟 How to open and configure Activity Usage Profile view in Primavera P6
🌟 How to change time-scale (days, weeks, months) and date display
🌟 How to modify bar colors and background shades for better visualization
🌟 How to show labor, non-labor, and material units or costs
🌟 How to compare planned, actual, and remaining values
🌟 How to apply and save your profile display preferences
🌟 How to switch between major and minor time divisions
🌟 How to use OpenShot 2.2.0 style visualization for resource performance graphs
00:00 – Introduction: Overview of Primavera P6 Display & Power Features
00:30 – Setting Up User Profile and Viewing Activity Layouts
01:10 – Adjusting Calendar and Time Scale Settings
01:40 – Selecting and Displaying Related Activities
02:20 – Managing Time Periods and Activity Visibility
02:55 – Configuring Activity Usage Profile and Data Display
03:35 – Showing Labor, Material & Expenses in Resource Profile
04:10 – Understanding Data Units: Labor and Non-Labor Resources
05:00 – Changing Chart Colors and Customizing Visual Display
06:00 – Editing Layouts and Applying Custom Colors for Clarity
07:10 – Displaying Actual vs Planned Values in Resource Graph
08:30 – Highlighting Major and Minor Lines in the Usage Profile
09:40 – Changing Background Colors and Visual Preferences
10:20 – Calculating Averages and Understanding Profile Data
11:15 – Updating Activity Information & Resource Assignments
12:00 – Switching Between Light and Dark Modes in P6
12:40 – Final Summary & Tips for Better Visualization in Primavera P6
⚠️🚩⛔DISCLAIMER:
This channel does not promote or encourage any illegal activities and all content provided by this channel is meant for EDUCATIONAL purposes only.
©️Copyright Disclaimer:
Under section 107 of the Copyright Act 1976, allowance is made for FAIR USE for purposes such as criticism, comment, news reporting, teaching, scholarship, and research. Fair use is a use permitted by copyright statutes that might otherwise be infringing. Non-profit, educational, or personal use tips the balance in favor of FAIR USE.
#PrimaveraP6 #PlanningP6 #ProjectControls #ScheduleManagement #ActivityUsageProfile #ResourceProfile #ProjectScheduler #PlanningEngineer #ProjectManagement #ConstructionPlanning #EPCProjects #OilAndGasProjects #InfrastructureProjects #PrimaveraP6Tutorials #PrimaveraP6Training #PrimaveraP6Tips #PrimaveraP6Course #PrimaveraP6Learning #PrimaveraP6Professional #PrimaveraP6Advanced #BaselineVsActual #ResourceManagement #CostManagement #WorkPerformance #PerformanceTracking #ProjectVisualization #PlanningAndScheduling #TimeScaleSettings #ColorCustomization #ProfileDisplay #ProjectControlTools #EngineeringProjects #CriticalPathMethod #ResourceGraph #PlanningEngineerLife #ProjectDashboard #DelayAnalysis #ActivityProfileView #P6Tutorial
Доступные форматы для скачивания:
Скачать видео mp4
-
Информация по загрузке: