Testing and Commissioning of AEG 125VDC Battery Charger
Автор: Electrical Insider
Загружено: 2025-07-05
Просмотров: 106
Testing and Commissioning Procedure for AEG DC Charger
1. Pre-Commissioning Checks
Before applying power to the system, perform the following checks:
1.1 Documentation Review
Verify all technical manuals, drawings, and datasheets are available and correct.
Confirm that the DC charger model matches project specifications (e.g., voltage, current rating).
1.2 Visual Inspection
Check for physical damages, loose wires, or missing parts.
Ensure all terminals are tight and properly labeled.
Inspect cabinet for proper grounding and cleanliness.
1.3 Mechanical Checks
Ensure ventilation fans (if any) are free from obstructions.
Check all panel doors close securely and have proper gaskets for IP rating.
1.4 Electrical Inspection
Confirm input AC supply rating (voltage, frequency, phase) is as per the charger specification.
Verify correct polarity of DC output terminals.
Measure insulation resistance using a Megger:
Between AC input and ground
Between DC output and ground
Acceptable value: 1 MΩ
2. Power-On Testing
2.1 Initial Energization
Ensure DC output is disconnected from the load.
Switch ON the main AC supply breaker.
Observe charger startup behavior (LEDs, HMI, display initialization).
2.2 Input Voltage and Current Check
Measure and verify AC input voltage at terminals.
Check input current and ensure it is within expected range.
2.3 Self-Test and Diagnostics
Allow the charger to complete self-check routines.
Review display or indicators for error/fault messages.
Acknowledge and clear any non-critical alarms.
3. Functional Tests
3.1 Output Voltage Test
Connect a dummy or resistive load.
Measure DC output voltage and verify it matches charger settings.
3.2 Output Current Test
Adjust load to draw current gradually.
Monitor current through the display or external meter.
Verify charger limits output as per nameplate rating.
3.3 Protection Function Test
Simulate:
Overvoltage condition
Overcurrent condition
Input failure
Output short circuit (if safe to test)
Verify system trips, alarms activate, and charger shuts down as designed.
3.4 Communication and Monitoring
Test any communication interfaces (Modbus, Ethernet, etc.).
Verify monitoring system receives real-time data (voltage, current, status).
Test remote shutdown/startup commands if applicable.
4. Battery Integration
4.1 Battery Connection
Confirm correct polarity and connection.
Monitor battery voltage and ensure the charger recognizes it.
4.2 Charging Profile Verification
Check the configured charging profile (Float/Boost/Equalize).
Verify voltage and current settings are appropriate for the battery type.
Monitor for any abnormal battery behavior (heating, swelling, etc.).
5. Final Checks and Documentation
5.1 System Stability Test
Run the charger under normal load for a minimum of 2–4 hours.
Monitor temperature, voltage, current, and alarms.
5.2 Parameter Logging
Record key commissioning parameters:
Input voltage/current
Output voltage/current
Charger temperature
Faults/alarm history
5.3 Handover and Reporting
Prepare a Test and Commissioning Report.
Get sign-off from client/QA/QC engineer.
Provide training or demonstration if required.
6. Safety and Compliance
Ensure all tests are performed with proper PPE.
Follow local electrical codes and standards (e.g., IEC 61851, NEC, etc.).
Confirm proper signage and labeling is in place before handover.
Доступные форматы для скачивания:
Скачать видео mp4
-
Информация по загрузке: