B takes 12 more days than A to finish a task. B and A start this task and A leaves the task 12 days before the task is finished. B completes 60% of the overall task. How long would B have taken to finish the task if he had worked independently?
48 days
36 days
28 days
32 days
Visit www.quantifiers.in to know more about us.
Join our Telegram channel here -
https://t.me/quantifiers
Join our Telegram group here:
https://t.me/+rHe5AZcGTRU1OThl
Facebook Group - / 370408017027604
Subscribe to our Instagram to get latest CAT Exam news- / quantifiers_cat
#CATDILR #DILRforCAT #CATPreparation #CATEXAM #NMATEXAM #SNAPEXAM #XATEXAM #IIMA #IIMB #IIMC #IIMK #IIML #IIMI #IIMAHEMDABAD #IIMBANGLORE #IIMCALCUTTA #IIMINDORE #IIMSHILLONG #IIMROHTAK #CATTIPS #CATEXAMTIPS #INSTAGRAM #VIRAL #REELS #quant #catexam #catexampreparation #catexamstips #shortcuts #catexamtime #math #shortcuts #viral #iim #iimahemdabad #cat2025 #catexam #cat2026 #aimcat #DailyDILRsets

Доступные форматы для скачивания:
Скачать видео mp4
-
Информация по загрузке: