Near Critical Path? What You’re Missing in Microsoft Project!
Автор: Dale Howard Microsoft Project MVP
Загружено: 2025-02-05
Просмотров: 706
Most project managers focus on the Critical Path, but what about the Near Critical Path? These tasks may not be fully critical yet, but they’re dangerously close—and ignoring them could derail your entire schedule.
In this video, I'll show you how to display both Critical and Near Critical tasks in Microsoft Project, so you can:
✔️ Identify tasks at risk of becoming critical
✔️ Adjust schedules proactively to prevent delays
✔️ Use custom filters to highlight Near Critical tasks
✔️ Gain better control over your project timelines
Whether you're new to Microsoft Project or an experienced PM looking for smarter scheduling techniques, this tutorial will help you stay ahead of potential bottlenecks.
For more Microsoft Project tips and tricks check out my blog
📰 https://www.dalehowardmvp.com/microso...
💎Download your Quick Access toolbar for Free Here https://www.dalehowardmvp.com/free-qu...
✅ Download your Free Quality filters here. https://www.dalehowardmvp.com/free-mi...
🖋️ If you find these tips helpful, please leave a comment or if you have other topics/questions about Microsoft Project leave it in the comments.
✉ If you have a topic or question you would like me to create a video about you can submit your questions at https://www.dalehowardmvp.com/contact...
To see other people's questions and my answers over the last 20 years, here's some links for the Microsoft Project message boards.
✓ Microsoft: https://techcommunity.microsoft.com/t...
▶️ LinkedIn: / 25618
If you're looking for a full course on Microsoft Project, check out one my OnDemand courses and you can be a Schedule Hero in just a week!
▶️ https://www.dalehowardmvp.com/microso...
🌐 My Website: https://www.dalehowardmvp.com/