Lake McQueeney Update: July 2025
Автор: Guadalupe-Blanco River Authority
Загружено: 2025-07-03
Просмотров: 4610
Since the last update video, construction work at McQueeney Dam has made a lot of progress. Key milestones include completing several large structural concrete pours for the for floor of the primary spillway where the spillgates will be installed. Construction of the concrete walls for the building where the new hydraulic power unit will be installed have also been completed.
What’s next? Over the next few weeks, the contractor is expected to complete the structural concrete work in the primary spillway and will begin installing the first of three spillgates. They will also begin the installation of the hydraulic power unit that operates the gates and the installation of the maintenance bridge that will span the river channel. The estimated timeline for estimated completion of the dam is early 2026.