Texas Water Resources Workload Spreadsheet Walkthrough
Автор: JMT Texas Pelicans
Загружено: 2025-12-04
Просмотров: 11
This video walks explains the functionality and basics of how to use the Texas Pelicans Workload forecasting spreadsheet.
Things I forgot to mention:
1) We have had issues with the spreadsheet operating off Sharepoint. We therefore recommend it being stored in ProjectWise instead.
2) Before hitting the month button, you should make sure there are no filters set on the "Project Centric Assignments Tab". This button moves the month forward but moves the data back so the hours will stay in the month that they were originally assigned. It may get flaky if there are filters set.
3). Do not add or delete rows on the Project Centric Assignments tab. It is set up to have a sufficient number of rows that should have enough space to assign the staff for most projects. If more are needed, just make sure you update the indexer column A and keep the formulas.