Here is another drone video from our partner Mike Atthis.
You can see the brickwork construction of the new parapet wall and reproduction chimney stacks is complete. Laying the new concrete floor slab continues and it now covers about 8 of the 22 casemates. This is actually the dividing level between the gun floor and the new storey that will be built on top but it is important for us fort enthusiasts because this reinforced concrete slab weatherproofs and consolidates the structure. A remarkable sight is the first two of the 1.9m diameter holes in the slab that are being cut for the spiral staircases which will connect the levels of each apartment. You can also see the massive core drills used for this job.