G99 CHP plant anti islanding testing for UKPN embedded generation compliance
Автор: Power ai
Загружено: 2024-01-21
Просмотров: 829
This is a record of G99 CHP plant anti islanding testing for UKPN embedded generation compliance comprising witnessed dry and wet testing to trip off the site generation when there is a loss of the incoming 33kV supply(s)
This covers a small aspect of the G99 requirements or shall we say working out what some of the G99 rather than G59 requirements are. I think a lot of us are still trying to establish what's needed (or is that just us?). Let's have a look at these loss of mains and backup trip tests.
We are hoping to commission the remote generation set down control in the future, where the grid operator (UKPN) will be able to reduce generation remotely on another companies power plant. Did you know they needed that?
From design through to certification, let's give you a glimpse inside the world of the industrial electrical environment covering systems, networks & apparatus up to 33kV and down to 24VDC!
These videos are for general information and entertainment purposes only. They are not intended as a set of instructions or guide on how to execute any electrical works. All our works are undertaken by competent and authorised engineers & technicians who have sufficient knowledge, experience & training to work safely. Electricity is dangerous! Any work on electrical systems must only be undertaken by those who are professionally competent to do so.
www.powerai.co.uk