Collaborative Solution to Deconstruction of Sydney's Iconic TCN-9 TX Tower by Marr Contracting
Автор: Marr Contracting
Загружено: 28 авг. 2023 г.
Просмотров: 6 300 просмотров
Mirvac engaged a team of international experts including Marr Contracting, Robert Bird Group and Kordia, to develop a solution for dismantling the iconic TCN-9 TX Tower in Willoughby, Sydney.
Built in 1965, the 233-metre transmission tower served as one of the 'Artarmon Triangle' broadcasting landmarks before being decommissioned in 2021. The deconstruction was part of Mirvac's plan to redevelop the site into a residential community.
Through an innovative and collaborative approach, the team designed and managed the complex process of dismantling the Sydney landmark safely and efficiently.
KEY HIGHLIGHTS:
•Innovative approach to dismantling a 233-metre lattice tower, a Sydney landmark for over 50 years.
•Collaborative effort with a leading team of Australian and international experts in engineering, dismantling and heavy lifting; and
•Successful craneage solution that reduced the lifting requirements from 90 planned lifts to just 36 - delivering a direct benefit in terms of time, cost and safety.
ABOUT MARR CONTRACTING
Marr Contracting offers specialist craneage solutions for complex construction projects including the de-planting, decommissioning and demolition sector.
LEARN MORE:
➡ Read the case study about the innovative approach to dismantling Sydney's iconic TCN-9 TX transmission tower: https://www.marr.com.au/projects/tx-t...
#marrcontracting #heavylifting #TCN9Tower #SydneyLandmarks #deconstruction #engineering #collaborativeprojects #Mirvac #infrastructure #Willoughby #towerdismantling #RobertBirdGroup #Kordia

Доступные форматы для скачивания:
Скачать видео mp4
-
Информация по загрузке: